Mba question papers for students

Mba question papers of production and operation management 2 of PGDBA program of symbiosis distance learning. question no 7 and 18 are in image file and best of luck in advance for Mba question papers and answers and read more about Sample question Papers.

MBA Question papers

Question 1 of 20 (Section: 1)

Question type: Multiple choice single select
Positive Marks: 2

Which time is determined by the forward pass computation method of determination of critical path?

1) Earliest expected time for each event
2) Duration of each activity
3) Latest allowable time for each event
4) Actual time for each event

Question 2 of 20 (Section: 1)

Question type: Multiple choice multiple select

Positive Marks: 2

JIT requires purchasing based on following philosophies:-

1) Purchasing from qualified source of suppliers.
2) Single source and long term contracts frequent deliveries.
3) Purchasing in large lots.
4) Frequent deliveries

Question 3 of 20 (Section: 1)

Question type: Multiple choice multiple select

Positive Marks: 2

Which are the main characteristics of project?

1) Clearly identifiable start and finish –ª
2) Repetitive
3) Uncertainties
4) Composed of large number of interrelated activities

Question 4 of 20 (Section: 1)

Question type: True or false

Positive Marks: 1

Process planning helps increase cycle time and defects while recognizing the value of individual contributions.

1) False
2) True

Question 5 of 20 (Section :1)

Question type: True or false

Positive Marks: 1

One major difference between CPM and PERT is the former’s adaptability for the projects where high degree of uncertainty prevails and activity times during performance are expected to vary considerably for certain activities.

1) False 2) True

Question 6 of 20 (Section: 1)

Question type: True or false

Positive Marks: 1

Overall time per piece includes even the time spent by the workman on observations of un-productive activities.

1) False 2) True

Question 8 of 20 (Section: 1)

Question type: Fill in the blanks

Positive Marks:1

The …………….Technique does not provide any allowance during planning and control.

1)Project Evaluation & Review Technique
2) Project Engineering & Resources Technique
3) Project Evaluation & Review Technique
4) Critical Path Method

Question 9 of 20 (Section: 1)

Question type: Fill in the blanks

Positive Marks:1

………….cost is the resultant of failure of the product delivered to the customer or put into the service.

1) External Failure
2) Appraisal cost
3) Hidden cost
4) Prevention Cost

Question 10 of 20 (Section :1)

Question type: FII in the blanks

Lot tolerance Percentage Defective ( LPTD )………… and are interrelated.

1) Acceptance Quality level
2) Consumer’s risk
3) Supplier’s risk
4) Producer’s risk

Question 11 of 20 (Section: 1)

Question type: Multiple choice single select

Positive Marks:2

What is the name of the document on which details of the process are recorded by the symbols and charting conventions?

1) Control plan 2) Flow sheet 3) Chart 4) Report

Question 12 of 20 (Section: 1)

Question type: FII in the blanks

Positive Marks: 1

The properties which are usually measured by comparison and any sample taken is classified either good or bad are called as

1) Constant
2) Fixed
3) Flexible
4) Variable

Question 13 of 20 (Section: 1)

Question type: Multiple choice single select

Positive Marks: 2

What do you mean by CPM?

1) Critical Path management
2) Critical Project management
3) Control of Project management
4) Critical Path method

Question 14 of 20 (Section: 1)

Question type : Fill in the blanks

Positive Marks:1

The……. Includes preventive maintenance activities which are carried out when the machine is still running.

Question 15 of 20 (Section: 1)

Question type: True or false

Positive Marks: 1

While numbering as per Fulkerson’s rule, arrows emerging from the initial event are deleted so as to create one or more initial events.

1) False 2) True

Question 16 of 20 (Section: 1)

Question type: True or false

Positive Marks: 1

Three time estimates are transformed into expected time before using it into a network.

1) True 2) False

Question 17 of 20 (Section: 1)

Question type: Multiple choice single select

Positive Marks:2

An approach to scheduling that tries to take capacity utilization into account, is known as

1) Critical Ratio Scheduling 2) Loading 3) Gantt Load Chart 4) Backward Scheduling

Question 19 of 20 (Section: 1)

Question type: Multiple choice multiple select

Positive Marks: 2

Which of the following classes of material needs quality inspection?

1) Raw Material 2) Bought- out parts 3) Stationary 4) Finished goods

Question 20 of 20 (Section: 1)

Question type: True or false

Positive Marks: 1

The activity percentage may be either based on past experience or a pilot study.
1) True 2) False

You can also find production and operation management 1 part mba question papers.